Authorisation to Release funding for recreation provisions secured under Section 106 Legal Agreement dated 11/12/08 in relation to Planning Permission 3PL/2007/1234/F (D38-19)

Decision Maker: Leader of the Council

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Purpose:

To seek agreement to release funds paid as a result of the S106 agreement dates 11 December 2008 for Phase Three Early Years Play Enhancement Project- Bullock Park, Shipdham.

Decision:

Breckland Council authorises the release of £6177.60 from the open space and recreation contribution held by the Council in accordance with a Section 106 Agreement dated 11 December 2008, in relation to Planning Permission 3PL/2007/1234/F for the Bullock Park Shipdham, Phase Three Early Years Play Enhancement Project.

Reasons for the decision:

The work is consistent with the requirements within the S106 Agreement as detailed within the report.

 

 

Alternative options considered:

1.     Fully fund the application as set out in the report.

2.     Do nothing.

Publication date: 04/09/2019

Date of decision: 04/09/2019

Effective from: 12/09/2019

Accompanying Documents: